Overview of completed projects

ProjectTaskActionsDuration
Pulpmill
Stendal
(Building construction)
Settling the claims (contractor) and counterclaims (employer) after finishing the work on site
  • Screening of the complete, relevant correspondence
  • Screening of the minutes of meeting
  • Clearing of the existing supplements
  • Generating additional supplements
  • Rating the counterclaims
  • Working out and negotiating a compromise line
6 months
Central station
Berlin
(Building construction)
Supporting the project team during erection phase
  • Observing and managing the correspondence
  • Participating in meetings
  • Announcing and canceling notices of obstruction as well as notices of reservation
  • Commenting or rejecting delay notifications
  • Generating and negotiating supplements, contract compliant
  • Co-ordinating the measuring of realized process
10 months
Power plant
Duisburg
(Plant construction)
Settling the claims (contractor) and counterclaims (employer) after finishing the work on site to prepare the final negotiations
  • Clearing of the existing supplements
  • Generating additional supplements
  • Rating the counterclaims
7 months

New power plant (lignite)
Grevenbroich-Neurath
(Plant construction)

Claim management and contract management on site (during erection and commissioning)
  • Observing and managing the contract-relevant correspondence
  • Announcing and canceling the notices of obstruction as well as notices of reservation
  • Continuesly comparing the target figures with the actual output (process)
  • Generating and negotiating supplements, contract compliant
48 months
New power plant (anthracite)
Hamburg-Moorburg
(Plant construction)
Claim management and contract management on site (during erection and commissioning)
  • Observing and managing the contract-relevant correspondence
  • Announcing and canceling the notices of obstruction as well as notices of reservation
  • Continuesly comparing the target figures with the actual output (process)
  • Generating and negotiating supplements, contract compliant
18 months

Crossroads Leutzscher Allee
Leipzig
(Civil works)

Supplements for additional works
  • Identifying and recording the additional work by comparing the target figures with the actual output
  • Creating the supplements, compliant to the VOB/B
1 month